PMI-ACP Question of the Week! 9 years 10 months ago #5154

  • Anne B
  • Anne B's Avatar Topic Author
  • Visitor
  • Visitor
Free PMI-ACP Exam Sample Question 01 (Agile Manifesto)

Question: Which of the following is not a value stated in the Agile Manifesto?

Which of the following is not a value stated in the Agile Manifesto?

A) Individuals and interactions over processes and tools
B ) Working software over comprehensive documentation
C) Customer communication over contract negotiation
D) Responding to change over following a plan

Scroll down to see the answer below the image ...



Correct Answer: C

This is a tricky question! Although each of these seems correct, one answer has been changed a bit from the actual words used in the Agile Manifesto.
Answers "A", "B" & "D" are from the Agile Manifesto word for word. The actual words used in the Agile Manifesto for answer "C" are Customer "collaboration" over contract negotiation, rather than Customer "communication" over contract negotiation, and this is why "C" is the correct answer to this question.

It is very important that you study and fully understand these Agile Manifesto values word for word because they help form the foundation of all Agile Project Management activities.

Reference: The Agile Manifesto
Moderators: Yolanda MabutasAnne BMary Kathrine PaduaJohn Paul BugarinSameer MendaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login