Which value is not used to calculate the estimated duration using three-point estimating techniques?
A. Most likely estimate
B. Standard estimate
C. Optimistic estimate
D. Pessimistic estimate
HINT: Look for the estimate that is not mentioned in the
PMBOK® Guide.
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
free.pm-exam-simulator.com/
and try the PM Exam Simulator free for 7 days.
Answer and Explanation:
The correct answer is B
Most likely, optimistic, and pessimistic estimates are the three types of estimates used to define an approximate value and range for an activity's duration using three-point estimating techniques.
Details for each option:
A. Most likely estimate
Incorrect. The most likely estimate is one of the three values.
B. Standard estimate
Correct. 'Standard estimate' is not a PMBOK® Guide term.
C. Optimistic estimate
Incorrect. The optimistic estimate is one of the three values.
D. Pessimistic estimate
Incorrect. The pessimistic estimate is one of the three values.
Reference:
Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) 201