fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: Question 35: Self assessment pre-course

Question 35: Self assessment pre-course 5 years 2 months ago #18734

  • Nadia Zandaqi
  • Nadia Zandaqi's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
Hi dear,

I notice that in Question 35: self assessment Q&A the Answer is A, but if I go to the Reference: A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) 248, 252 , it mentioned the project budget = cost baseline + Management reserve ; so I feel there is a contradiction , can any one clarify this point for me.

Best Regards,
Nadia
Moderators: John Paul Bugarin

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login