You are using the precedence diagramming method to sequence the project schedule activities in your activity list. Of the following logical relationships between project activities, which is the most common?
A. Finish to finish
B. Finish to start
C. Start to start
D. Start to finish
Hint: By default, no project activities overlap, and each task must be completed before the next one can begin.
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Want more CAPM exam sample questions? Simply sign up to our Free PMP Exam Simulator by visiting
www.pm-exam-simulator.com/pmp-exam-simul...e-pmp-exam-simulator
where we offer updated questions.
OSP International LLC has been reviewed and approved as a provider of project management training by the Project Management Institute (PMI)®. As a PMI Registered Education Provider (R.E.P.), we have agreed to abide by PMI® established quality assurance criteria.
“PMI” and “CAPM” are registered marks of Project Management Institute, Inc.
Correct Answer: B
A finish-to-start logical relationship is one in which is successor activity cannot start until a predecessor activity has finished. This logical relationship is the most common and is often the default.
Exam Reference:
A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) 189-190