Which of the following statements is true about the change control board?
A. A change control board is a group responsible for reviewing and approving or rejecting changes to the project.
B. The change control board is responsible for tracking change status to ensure all approved changes are correctly implemented.
C. The change control board should not include the project team to ensure objective decisions are made.
D. Every change should be analyzed and approved by the change control board before being implemented.
Hint: Remember the concept of the change control board.
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Want more CAPM exam sample questions? Simply sign up to our Free PMP Exam Simulator by visiting
www.pm-exam-simulator.com/pmp-exam-simul...e-pmp-exam-simulator
where we offer updated questions.
OSP International LLC has been reviewed and approved as a provider of project management training by the Project Management Institute (PMI)®. As a PMI Registered Education Provider (R.E.P.), we have agreed to abide by PMI® established quality assurance criteria.
Correct Answer: A
In project change management, a change control board (CCB) may be required to review and approve for changes. Normally, members of the change control board come from various departments to ensure the impact of change requests to all aspects of the project and other factors outside the project are considered and analyzed before making a decision.
Reference:
PMBOK® Guide– Sixth Edition, Project Management Institute Inc., 2017, Page(s) 115
“PMI” and “CAPM” are registered marks of Project Management Institute, Inc.