fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: Free CAPM® Exam Sample Question

Free CAPM® Exam Sample Question 3 years 8 months ago #27221

  • Arjie Maghanoy
  • Arjie Maghanoy's Avatar Topic Author
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 182
  • Karma: 21
  • Thank you received: 66


The failure rate is an example of which of the following?

A. Quality metrics
B. Process metrics
C. Quality checklists
D. Quality control measurements

HINT: Note that failure rate is a product attribute.

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days.

Answer and Explanation:
The correct answer is A.

Quality metrics are usually about a project or product attributes and used in both quality assurance and quality control to ensure the project meets the quality objectives such as on-time milestones, failure rate, or requirement stability. While quality control measurements and process metrics are about the process indicators, a quality checklist is a list used to verify that a set of steps has been performed.

Details for each option:

A. Quality metrics
Correct. Quality metrics are used to measure important attributes of the project and product with the predefined tolerance. Examples of quality metrics are tasks completed on time, requirement stability, the percentage of requirements covered by test plans, and the like.


B. Process metrics
Incorrect. Process metrics are defined to measure the quality and performance of a process, not a product. As the failure rate is about product quality, it is not an example of process metrics.

C. Quality checklists
Incorrect. The failure rate is a metric, not a checklist.

D. Quality control measurements
Incorrect. Quality control measurements are the measurements of process metrics, not product metrics. Therefore, the failure rate is not included in quality control measurements.

Reference: A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) 287
Last edit: by John Paul Bugarin.
Moderators: John Paul Bugarin

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login