fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: Free CAPM® Exam Sample Question

Free CAPM® Exam Sample Question 3 years 10 months ago #26078

  • Arjie Maghanoy
  • Arjie Maghanoy's Avatar Topic Author
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 182
  • Karma: 21
  • Thank you received: 66


In a software development project, if the developers could start fixing bugs two days after the testers begin testing, this arrangement implies:

A. A start-to-finish relationship with a 2-day lead
B. A start-to-start relationship with a 2-day lead
C. A start-to-finish relationship with a 2-day lag
D. A start-to-start relationship with a 2-day lag

HINT: Note the difference between lead and lag.

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days.

Answer and Explanation:
The correct answer is D.

A lag is the amount of time whereby a successor activity will be delayed with respect to a predecessor activity. Thus, if the development team could start resolving issues two days after the testers started testing, it means that the two tasks have a start-to-start or SS relationship with a 2-day lag.

Details for each option:

A. A start-to-finish relationship with a 2-day lead
Incorrect. A situation where bug fixing can start 2 days after testing is a start-to-start relationship.

B. A start-to-start relationship with a 2-day lead
Incorrect. Lead is the amount of time that a successor activity can be advanced from a predecessor activity. In this case, it is a start-to-start relationship where the successor activity is being delayed, not advanced.

C. A start-to-finish relationship with a 2-day lag
Incorrect. Bug fixing can start 2 days after testing starts is a start-to-start relationship.

D. A start-to-start relationship with a 2-day lag
Correct. Lag is the amount of time that the second activity can be delayed with respect to the previous activity. Thus, the question scenario describes a start-to-start relationship with 2- day lag.

Reference: A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) 192-193
Last edit: by John Paul Bugarin.
Moderators: John Paul Bugarin

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login