fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Change Request

Change Request 4 years 8 months ago #20344

  • Saubhagya Raizada
  • Saubhagya Raizada's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
Hi,

I was wondering that if a Change Request is required if the following occurs:

1. Project is going to be finished with achieving the project scope before the date outlined in the approved Schedule baseline?
2. Project is going to incur less cost then what was determined in approved Cost baseline?

Regards,
Saubhagya

Change Request 4 years 8 months ago #20361

  • Harry Elston
  • Harry Elston's Avatar
  • Offline
  • Platinum Boarder
  • Platinum Boarder
  • Posts: 473
  • Karma: 27
  • Thank you received: 146
Saubhagya,

Neither activity requires a change request. Both activities are within the baselines of the project and would not create a change in baseline.

Bonus that the Project Manager looks like a hero because they completed the project ahead of schedule and under busget.

Harry
+++++
Harry J. Elston, Ph.D., CIH, PMP
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul Bugarin

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login