CORRECT ANSWER: B
Discretionary dependencies are often established by the knowledge or best practices regarding project work. It suggests desired sequences in completing project work although some other options are also acceptable. Thus, discretionary dependencies provide opportunities for the project team to compress the schedule by fast tracking.