fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: 5th E.: Critical path method shown in figure 6-18

5th E.: Critical path method shown in figure 6-18 10 years 11 months ago #3928

  • Daniel Blossey
  • Daniel Blossey's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Por el placer de vivir viajando!
  • Posts: 32
  • Thank you received: 1
Hi,

I am referring to video "L06.06.2_Develop_Schedule_HR.mp4" in which the critical path method is shown. This also links to figure 6-18 of the PMBok Guide, 5th edition.

I do not understand all the numbers inside the activity boxes. e.g., activity B has a float of 5 days. Do you have an example which explains all the numbers, forward and backward pass, float etc. in more detail using the presented schedule model format?

Thanks, Daniel from Germany!

5th E.: Critical path method shown in figure 6-18 10 years 11 months ago #3929

  • Daniel Blossey
  • Daniel Blossey's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Por el placer de vivir viajando!
  • Posts: 32
  • Thank you received: 1
Ah, I think I have the answer: The float or free float is the difference of Late Start and Early Start date. So for activity B it is 11 - 6 = 5 days. Result: The project manager can wait 5 more days for activity B without delaying the successor activity D.

What is the difference between total and free float?

5th E.: Critical path method shown in figure 6-18 10 years 11 months ago #3930

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1997
  • Karma: 121
  • Thank you received: 618
Daniel,

Please watch lesson L06.08 Network Diagram of The PM PrepCast. That shows all the steps in detail.
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC

5th E.: Critical path method shown in figure 6-18 10 years 11 months ago #3931

  • Daniel Blossey
  • Daniel Blossey's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Por el placer de vivir viajando!
  • Posts: 32
  • Thank you received: 1
Dear Cornelius,

Thanks and happy Nikolaus!

Ah, I missed this file. Is there a log file which shows when you have updated or added your videos? Because I may be out of sync with the videos after a while.

Thanks!

5th E.: Critical path method shown in figure 6-18 10 years 11 months ago #3933

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1997
  • Karma: 121
  • Thank you received: 618
Daniel,

Please open up your student workbook PDF document. That is L00.10 of the PrepCast. It should contain answers to most general, administrative, and technical questions of this kind.
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul Bugarin

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login