Free PMI-ACP® Exam Sample Question 41
In terms of the decomposition of requirements on an Agile project the artifact that contains release plans as its first level of decomposition is referred to as a?
A) Product Roadmap
B) Release Backlog
C) Product Backlog
D) Sprint Backlog
HINT: This is the second Agile Artifact that is created during the Initial Strategy Meeting on an Agile Project.
Scroll down to see the answer below the image ...
Correct Answer: A
The Product Roadmap is the second Agile Artifact that that is created during the Initial Strategy Meeting on an Agile Project. It is a visual timeline of major product features that support the Product Vision Statement, broken down into releases. This will enable the Initial Strategy Meeting attendees to see the ‘big picture’ of when these major product features will be developed and released over the life of the entire project.
Reference: The Scrum Field Guide: Practical Advice for Your First Year, Mitch Lacey, 2012