In terms of the decomposition of requirements on an Agile project, the artifact that contains release plans as its first level of decomposition is referred to as a?
A) Product Backlog
B) Release Backlog
C) Product Roadmap
D) Release Roadmap
Scroll down to see the answer below the image ...
Correct Answer: C