Which of the following Agile meetings is used to synchronize an Agile project team's activities to ensure they are all working toward a common iteration goal?

A) Daily Standup Meeting                       
B) Iteration Review Meeting
C) Iteration Planning Meeting
D) Iteration Retrospective Meeting


Scroll down to see the answer below the image ...

Books above the head


Correct Answer: A

When you think about the Agile Daily Standup Meeting, remember the term 'synchronize'.  This Agile meeting is used to synchronize an Agile project team's activities to ensure they are all working toward a common iteration goal.

Reference: The Scrum Field Guide: Practical Advice for Your First Year, Mitch Lacey, 2012.