Free PMI-ACP® Exam Sample Question 20
On your Agile project you have just completed the creation of a potentially shippable product increment. The time it took to create this product increment is referred to as?
A) Actual Time
B) Cycle Time
C) Lead Time
D) Real Time
Scroll down to see the answer below the image ...
Correct Answer: B
Cycle Time refers to the time it takes (from beginning to end) to complete the creation of a potentially shippable product increment.
Reference: Agile Project Management with Scrum, Ken Schwaber, 2004.