Free PMI-ACP® Exam Sample Question 80

An agile team finished coding for the current iteration. Which of the following is a continuous process improvement ceremony that the team will now attend?

A. Release planning meeting
B. Iteration retrospective meeting
C. Product demonstration meeting
D. Iteration planning meeting

Hint: Which meeting reflects upon the past iteration to develop improvement plans?


Scroll down to see the answer below the image ...

dup123


Correct Answer: B

Answer and Explanations:

Answer A: Incorrect. The release planning meeting is held to plan the work for the entire release and not to reflect on the recently completed iteration.

Answer B: Correct. The iteration retrospective meeting is an example of a continuous process improvement ceremony on an agile project.

Answer C: Incorrect. The product demonstration meeting is a product-centric meeting held at the end of each release to demonstrate the product features that have been completed during that release

Answer D: Incorrect. The iteration planning meeting is held to plan the work for each iteration. The iteration planning meeting is not a continuous process improvement ceremony.

Exam Reference: Agile Practice Guide, Project Management Institute Inc., 2017, Page(s) 50-51; see also Agile Retrospectives: Making Good Teams Great, Esther Derby, Diana Larsen, 2006

 

 