Free PMI-ACP® Exam Sample Question 75

A team lead is currently demonstrating a potentially shippable product increment for project stakeholders. Which agile meeting is being conducted?

A. Iteration review meeting
B. Daily standup meeting
C. Iteration retrospective meeting
D. Iteration deliverables meeting

Hint: The stakeholders examine or inspect the product increment during this meeting.


Scroll down to see the answer below the image ...

iStock 1137923596


Correct Answer: A

Answer and Explanations:

Answer A: Correct. The iteration review meeting is a product-oriented meeting held at the end of the iteration to demonstrate product increments completed within that iteration.

Answer B: Incorrect. The daily standup meeting is used to synchronize the team on a daily basis during the iteration and not to review the product increment developed during the iteration.

Answer C: Incorrect. The iteration retrospective meeting is held at the end of each iteration and is used to review current processes to improve performance.

Answer D: Incorrect. An ‘iteration deliverables meeting’ is a fake term made up for this question.

Exam Reference: Agile Practice Guide, Project Management Institute Inc., 2017, Page(s) 55; see also PMI-ACP Exam Prep, 2nd Edition: A Course in a Book for Passing the PMI Agile Certified Practitioner (PMI-ACP)® Exam, Mike Griffiths, 2012, Iterations

 

 